6. Reserve and contingency strategy

Reserves are a vital part of the Council’s financial strategy and are held to create long term budgetary stability and to manage risk. They enable the Council to manage change without undue impact on Council Tax and are a key element of its financial standing and resilience.

The Council continues to face a number of financial risks and therefore holds earmarked reserves and a general fund reserve in order to mitigate future financial risks. There are two main types of reserves:

  • Earmarked Reserves – which are held for identified purposes and are used to maintain a resource to provide for expenditure in a future year(s)
  • General Reserves – these are held for ‘unforeseen’ events

The Council maintains reserves both for its General Fund activities and in respect of schools. School balances belong to maintained schools and will be subject to localised plans.

Details of the Council’s reserves (excluding the Dedicated Schools Grant) and their forecast balances are summarised in the table below. These will be reviewed in light of the outturn and future calls on the reserves.

Reserve Balance Forecast

 2027/28
£’m
2028/29
£’m
2029/30
£’m
2030/31
£’m
Earmarked Reserves37.65038.18438.71839.252
Community Infrastructure Reserve1.2242.1743.1744.174
Schools (Excluding DSG) Balances1.7401.3400.9400.540
General Fund Reserve14.36014.36014.36014.360
Total Reserves54.97456.05757.19158.325

The amount of reserves held is a matter of professional judgment as determined by the Councils s151 officer (the Director of Finance & Corporate Services). His assessment considers the reasons why reserves are maintained, and the Council’s potential financial exposure to risks including demographic, inflationary and legislative/regulatory changes.

Reserves are one-off money and therefore the Council must avoid using reserves to meet on-going financial commitments other than as part of a sustainable budget plan. The Council must balance the opportunity cost of holding reserves in terms of Council Tax against the importance of interest earning and long-term future planning. It is imperative that reserves are replenished in the short to medium term in order to improve financial resilience against future increasing uncertainty. However, opportunities are limited as this can only be achieved if the Council identify further saving, efficiency, transformational or income opportunities.

Alongside the reserves the Council includes within its recurring revenue budget a revenue contingency which is utilised before reserves. Contingency was increased to a level of £5.000m for 2026/27 only, reverting back to £2.700m in future years. There is no change to the assumptions reported to Public Cabinet in February 2026.  Contingency of £2.700m is currently set aside for each year of the Medium Term Financial Strategy.

 2027/28
£’m
2028/29
£’m
2029/30
£’m
2030/31
£’m
Contingency - Planning Assumption reported to Cabinet February 20262.7002.7002.700 
Inclusion of 2030/31   2.700